FTN design & development specification (D&D)

SP FTN (D&D) 005

Jointing, Terminating and Testing Optical Fibre and Copper Telecommunications Cables

Issue 4.6, Feb 2009 · FTN D&D specs & typical drawings

The installer's rulebook for joining, terminating and commissioning-testing FTN fibre and copper cables. Designers use it for sheath gap rules, splice and termination arrangements, free-issue kit names, splice loss acceptance figures and the OTDR/insertion loss test regime that the design pass marks feed.

Clause map — what each clause deals with

1PurposeWhat the spec covers and who must work to it.
2ScopeApplies to contractors' staff jointing, terminating and testing FTN & GSM-R cables; includes standards, test parameters and proformas.
3Reference DocumentationDocuments referred to: 008, 009, 010, copper cable spec, laser safety standard.
4Definitions & AbbreviationsAcronyms (BFA, BOP, CSM, IDC, ILM, MB, ODF, OTDR, VL, VT) and definitions of node types, BOP, DI-SAC, fibre section, UP end etc.
5GeneralWho produces the detailed design, free-issue cables, interfacing with existing cables, contractor's plant and test equipment calibration duties.
5.9Free Issue materialsList of kit Network Rail normally free-issues: copper and fibre cables, joint closures, gapping kits, cabinets, IDC modules, termination kits, BOPs, repeater pulled fibre.
5.10Work in ac Electrified AreasInduced voltage hazards in ac areas: limits on continuous metallic lengths, screening conductors in place first, keep metallic elements earth-free, Hot Wire Working.
6JointingAll jointing requirements for fibre and copper cables.
6.1GeneralJoint bay siting, vertical closure entry, twin-sheath sealing, traction hazards, and armour gapping and isolation practices (ungapped length limits, gap before buildings, moisture barrier, CSM).
6.2Optical fibre jointingFIST GCO2 closures, security, fibre colour codes for standard and DI-SAC cable, splicing rules, cross-splice schedule, temporary spur closures, DI-SAC insulation, repeater bundled fibre, ZHLS.
6.3Copper JointingTelsplice connectors, pair-to-pair jointing, staggering, XAGA 500 closure, through joints only, UP end marking, continuity bond and moisture barrier treatment by electrification type, ZHLS change-over.
7TerminationAll termination requirements for fibre and copper cables.
7.1GeneralCable securing, gel cleaning, bottom entry preference, sheath gap before cabinets/buildings, bend radius, where to strip armour.
7.2Optical fibre terminationsFibre termination arrangements including DI-SAC and GSM-R repeaters.
7.2.1GeneralODF units and height, tray loading, splices per tray, SC/APC spec, collets, which cables are fully terminated, storing unused fibres, pigtail return, fibre storage length.
7.2.2DI-SACThe special DI-SAC manifold that insulates metallic parts and redistributes 2x12 fibres into six 4-fibre tubes for standard trays.
7.2.3GSM-R RepeatersRepeater enclosures on monopoles or wing walls, pulled bundled fibre through PE tube and gland, BPE/O closure, trunking, no termination at repeater end.
7.3Copper terminationModule types by environment, linking plugs, gel and twist, moisture barrier termination incl. TEHs, cabinet dressing, jumpers, vertical A/B/C allocation, mileage changes, VL/VT pairs.
7.4Tunnel Termination BoxesWhat tunnel termination boxes are and why they are used for 10 pair tails in long tunnels.
7.5Ten pair tail cables to tunnel boxesWhere tunnel box tail cables terminate in the next cabinet/BOP and moisture barrier isolation.
7.6Cable Termination Order and Termination Labelling In Core Nodes and Access NodesPair 1 at the top, one vertical per cable, order of terminating multiple cables, and what the termination label must show.
7.7Jumper WireJumper wire standard, colour code by application, A/B leg convention, and earth testing/bonding of MDF to the MSE.
7.8Installation of HDSL Repeaters and Termination of CircuitsPointer to the work instruction covering HDSL repeater housings on cabinets.
8Marking and RecordsLabel to 016, record to 017.
9TestingCommissioning test principles: witnessing and notice, cover page, testing in agreed sections.
9.2Optical Testing – GeneralDesign-derived pass marks per section, use of 1 km buffer fibres at both ends, backscatter after termination, connector cleaning.
9.3Copper cable testing – generalSafety of HV copper tests, test plan approval, discharging cables, section extents from the design.
10Submission of Test ResultsSelf-assessing spreadsheets, submission timescale, OTDR trace format (.SOR, Telcordia/Bellcore), trace scaling.
11Condition Testing of Cables While on the DrumWhen drum condition testing is needed, the fibre and copper tests involved (moisture barrier IR/continuity, single-direction backscatter, conductor IR) and the report content.
App ASchedule of Optical TestsOptical test regime: OTDR set-up (pulse width, range, markers, refractive index), splice loss acceptance tiers, insertion loss method, permissible loss values, bare-end and repeater tests.
App BSchedule of Copper Cable TestsCopper test regime: continuity and resistance, moisture barrier IR/continuity, conductor IR, HV breakdown, attenuation incl. HDSL, NEXT, psophometric noise, temperature correction table.
App CTest Sheet Pro Forma – Optical FibreSuperseded by the live self-assessing spreadsheet.
App DTest Sheet Pro Forma – CopperSuperseded by the live self-assessing spreadsheet.

Standards this one points to