FTN design & development specification (D&D)
SP FTN (D&D) 004
Renovation and Construction of New Cable Route
Issue 9.2, Feb 2009 · FTN D&D specs & typical drawings
Route-works specification for FTN/GSM-R contractors: how to build new lineside cable route (DI-SAC, concrete troughing, elevated route, ducts, manholes, cabinets) and renovate existing troughing. Designers use it to know what the detailed design must specify.
Clause map — what each clause deals with
| 1 | Abbreviations | List of acronyms used in the spec (GLT, DI-SAC, UTX, BOP, etc.). |
| 2 | General | Background to the FTN/GSM-R route works, who produces the detailed design, contractor material and Product Acceptance duties, intended route design life. |
| 3 | Cable Route | What counts as cable route and the contractor's handover duty for a clean, dressed route. |
| 3.1 | General | Types of route covered and the requirement that works follow the detailed design. |
| 4 | Contractual Limits of Work | What tendered rates include, site supervision expectations and temporary ownership of the route under handover/handback. |
| 4.1 | Renovation of Existing Routes | Pointer to section 8. |
| 4.2 | Construction of New Route | Pointer to section 7. |
| 4.3 | Route Material Depots | Contractor's responsibilities for depot security, receipt, damage records, stock control and sorting returned materials. |
| 5 | Extent of Network Rail's Assistance | What Network Rail provides: liaison representation and drawings. |
| 6 | Possession of Running Lines | Possessions are dealt with in the tender documents, not here. |
| 7 | Construction of New Cable Route | Main section on building new route of all types. |
| 7.1 | General | Siting rules for new route: distance from running rail (table), reduced clearance near structures, concessions, catch points, buffer stops, ballast cleaner access, ramped supports past drains. |
| 7.2 | The Extent of the Works | List of work activities included in new route construction: excavation, posts, duct routes, manholes, metalwork, supports, vertical routes. |
| 7.3 | Double Insulated Super Armoured Optical Fibre Cable (DI-SAC) | Everything about laying DI-SAC as a surface-secured fibre route: product, securing, interfaces, crossings, hazards, suppliers. |
| 7.3.1 | Introduction | What DI-SAC is and where it is approved for use (fibre-only areas). |
| 7.3.2 | Product Overview | Cable construction summary and the closure kit used for jointing; jointing instructions are in 005. |
| 7.3.3 | Installation | Installation objectives, end sealing, bending radius limit, scratch burying to avoid trip hazards, marking anchor points. |
| 7.3.4 | Securing the DI-SAC | Spacing of securing positions on straight and curved track, ground anchor depth and testing, stainless ties, J-hangers at platforms, approval for fixing on structures. |
| 7.3.5 | Interfaces with Cable Routes | How DI-SAC enters existing troughing via knockouts or open ends, sill protection, sealing against vermin, anchoring before entry, crossing sidings in GLT. |
| 7.3.6 | Interfaces with Bridges and Viaducts | Options for taking DI-SAC across structures and the approval route for fixing methods. |
| 7.3.7 | Interfaces with UTX and URX Manholes | Keeping DI-SAC continuous through under-track and under-road crossings without extra joints. |
| 7.3.8 | Interfaces with Cable Joint Bays | Joint bay arrangement for a DI-SAC joint (figure) and anchoring either side of the bay. |
| 7.3.9 | Sheath Gaps | Why sheath gaps are needed in DI-SAC, where their positions come from, and the trough and anchoring used to house them. |
| 7.3.10 | Foot Crossings and Farm Crossings | Using existing ducts or troughing at crossings, or burying DI-SAC in split duct where no capacity exists. |
| 7.3.11 | Vehicular Access Points | Burying DI-SAC in twin HDPE ducts at vehicle crossings, with a sealed spare bore and inspection pits. |
| 7.3.12 | Creation of Hazards and Obstructions | Keeping DI-SAC clear of SPTs, lineside telephones, cabinets, standing areas and bridge parapets. |
| 7.3.13 | DI-SAC Product Supply Details | Supplier contacts for ground anchors and stainless steel ties. |
| 7.3.14 | DI-SAC Ancillary Photographs | Photos of a ground anchor and a J-hanger. |
| 7.4 | Directly Buried Sub-duct (DBS) | DBS is largely withdrawn; residual rules for vehicle crossings and supplier details for sub-duct, lubricant and pulling grips. |
| 7.4.1 | Introduction | Sub-duct no longer used as primary trackside protection except short buried runs. |
| 7.4.2 | Occupation Crossings, Foot Crossings and Farm Crossings | DBS not used at these crossings; points to 7.5.1.12. |
| 7.4.3 | Vehicular Access Points | Burial depth, allowable deflection and spare sealed duct at vehicle crossings. |
| 7.4.4 | Creation of Hazards and Obstructions | DBS must not create hazards or obstructions. |
| 7.4.5 | DBS Product Details | Supplier contacts for sub-duct, couplers, lubricant, pulling grips and fused swivels. |
| 7.5 | Reinforced Concrete Troughing | Rules for laying concrete GLT, joint bays and node entries. |
| 7.5.1 | General | Troughing supply, breakages, machine cutting, lid stagger, set-in height, buried route use, crossings, vandal areas, ballast, traction bonds, route supports. |
| 7.5.2 | Joint Bays | Joint bay construction for copper (parallel bays) and fibre (GCO2-F closures, drawings), green zone access, sealing T-pieces. |
| 7.5.3 | Cable Route Interface with Nodes | Cable entries into nodes per the detailed design and node entry drawings. |
| 7.6 | Elevated Cable Route | When elevated route is used and how it is built. |
| 7.6.1 | General | Elevated route only where GLT is unsuitable; materials, storage on site, buried services search before posts. |
| 7.6.2 | G.R.C., G.R.P. and U.P.V.C Route Construction | Post setting, bracket height, vertical routes on racking, approvals, non-metallic clamps, lid stagger, vandal banding, metalwork protection. |
| 7.7 | Retaining Walls for Joint Bays & Cabinets | Embankment platforms preferred over retaining walls; wall materials and thickness; concrete ballast boards; buried services search. |
| 7.8 | Construction of New Manholes | Manhole construction materials and a table of sizes, cover classes and drawings by location. |
| 7.8.1 | General | Materials for manholes, acceptance of alternatives, and the location/dimension/class table. |
| 7.8.2 | Covers and Frames | Cover and frame standard and the test loads for each class. |
| 7.9 | Buried Duct Routes | Requirements for new duct routes in platforms, walkways, public crossings and under track. |
| 7.9.1 | Requirements for All Duct Routes (Except DBS) | When new ducts are justified, duct type, UTX warning tape, bedding/backfill drawing, bend limits, mandrel testing, draw rope. |
| 7.9.2 | Routes Through Station Platforms | Cover depth, offset from platform edge, reinstatement timescales, manholes at ramp top and toe, spur feeds to buildings, site protection. |
| 7.9.3 | Hard Surface Walkway Duct Routes | Cover depth and reinstatement rules for ducts in hard walkways. |
| 7.9.4 | Public Crossings | Duct works across public rights of way: statutory requirements and cover depth. |
| 7.9.5 | Undertrack Crossings | UTX built to the company standard and drawing; under-track boring needs civil engineer approval. |
| 7.10 | Installation of Distribution Cabinets, DSL Repeater Housings and Pole-Mounted Boxes | Free-issued cabinets and BOPs, concrete bases, positioning beside the route, cable entry from below, no drilling, when hard-standing is needed. |
| 7.11 | Installation of Plant for GSM-R Tunnel Repeaters | Route, joint bays and closure mounting for tunnel repeater feeds; bend radius control for cables and tubing. |
| 8 | Renovation of Existing Cable Routes | Minimum-intervention approach to getting cables into existing troughing and elevated routes. |
| 8.1 | General | Prefer tilting the lid to insert cables where route condition allows; lid tilting tool. |
| 8.2 | Renovation of Existing Reinforced Concrete Troughing | Full renovation tasks: exposing route, replacing damaged units, imperial to metric swaps, protecting cables, fragile signalling cables, lifting/relaying, realigning, clearing out, manholes, bonds, earth farm tests. |
| 8.2.6 | The Lifting and Relaying of Existing Ground Level Concrete Troughing Routes | Preconditions and finish quality for lifting and relaying GLT, protecting cables while out of route. |
| 8.2.7 | The Realigning of Existing Ground Level Concrete Troughing Routes | Realignment is defined by survey and design; same protection and finish rules; moving apparatus cases needs approval. |
| 8.2.8 | Clearing Out Route | Removing debris, recovering materials, refurbishing UTX/URX, platform routes, supports, ballast boards and retaining walls. |
| 8.2.12 | The Renovation of Existing Manholes | What manhole renovation typically covers and when covers and frames get replaced. |
| 8.2.13 | The Demolishing and Rebuilding of Existing Manholes | Manholes beyond renovation are rebuilt. |
| 9 | Work in Tunnels and Restricted Areas | Civils approval, possessions, materials handling, lighting, limited space, and cable support in tunnels (hangers vs continuous support, DI-SAC on hangers). |
| 10 | Timbering | Shoring and support of excavations and when it may be left in place. |
| 11 | Anti-Corrosion Protection for Ferrous Metalwork | Galvanising and protective treatment of installed and site-fabricated steelwork. |
| 12 | Surplus and / or Scrap Material Recovery and Disposal | Contractor responsibility for surplus, scrap and spoil. |
| 12.1 | Disposal of Spoil | Where and how deep clean spoil may be spread on level ground, embankments and cuttings (figures); method statement. |
| 12.2 | Waste Water | Mostly removed; contractor to describe waste water and sludge disposal method. |
| 13 | Materials Supplied by the Contractor | Pointer to section 2. |
| 14 | Materials Supplied by Network Rail | Free-issue schedule available on request. |
| 15 | Security and Conduct of Staff on Site | PTS, COSS safe system of work, PPE, keeping walkways clear. |
| 16 | Access | Access via private land, notifying access points, fence ladders, fencing, station access. |
| 17 | Handling of Materials Containing Asbestos | Approved sub-contractor, notification, disposal as special waste, handback after air monitoring. |
| 18 | Buried Services Searches | Follow the company process for locating buried services before breaking ground. |
| 19 | Reference Documentation | Table of referenced standards with old and new reference numbers. |
| 20 | Definitions | Meaning of route materials, rules of the route, main route and spur route. |
| App A | Drawings | List of route support, node entry, UTX/URX, retaining wall, staging and crossing drawings referenced in the spec. |
Standards this one points to
- DR FTN (D&D) 015
- DR FTN (D&D) 016
- DR FTN (D&D) 035
- DR FTN (D&D) 036
- DR FTN (D&D) 037
- DR FTN (D&D) 038
- DR FTN (D&D) 039
- DR FTN (D&D) 040
- DR FTN (D&D) 041
- DR FTN (D&D) 042
- DR FTN (D&D) 043
- DR FTN (D&D) 044
- DR FTN (D&D) 052
- DR FTN (D&D) 053
- DR FTN (D&D) 060
- DR FTN (D&D) 061
- DR FTN (D&D) 067
- DR FTN (D&D) 1001
- DR FTN (D&D) 1002
- DR FTN (D&D) 1003
- DR FTN (D&D) 1004
- DR FTN (D&D) 1005
- SP FTN (SU) 001
- SP FTN (D&D) 005
- SP FTN (D&D) 007
- SP FTN (D&D) 009
- SP FTN (D&D) 013
- SP FTN (D&D) 006