Rail Telecoms One Stop

Level 3 work instruction

NR/L3/TEL/30162

Work Instruction for Jointing, Terminating and Testing Optical Fibre Cables

Issue 3, 03 September 2022 · Fibre design

Clause map — what each clause deals with

1PurposeWhat the instruction is for: jointing, terminating and site acceptance testing of fibre cables
2ScopeWhat it covers: jointing/termination practice and the optical test methods and pass values
3AbbreviationsAbbreviations (OTDR, ILM, CD, PMD, DISAC and so on)
4DefinitionsDefinitions used in the instruction
5.1GeneralHow loose-tube cable is built (tubes, fibres, strength member) as background to jointing
6.1GeneralWhy conductive sheath elements are gapped — traction and other electrical hazards
6.2Continuous Electrical PathWhat a sheath gap physically is and when the continuous path length triggers one
6.3Rail Return SystemsSheath gapping in AC areas with rail-return traction
6.4Booster Transformer or Autotransformer SystemsSheath gapping in booster-transformer or autotransformer areas
6.5JointsElectrical isolation of strength members and armour at joints
6.6Metallic ArmouringGapping armour where a cable enters a building or lineside housing
6.7DISAC and DISAF CablesInsulation and gapping of DISAC/DISAF cables
7.1GeneralWhat a joint closure must be and how cables enter it
7.2Fibre Tubes and ribbonsRouting tubes and ribbons inside the closure without kinking
7.3Optical FibresRouting fibres in cassettes to avoid stress and microbends
7.4Splice CassettesHow splice cassettes are used and ordered to ease later work
7.6Fibre, tube, ribbon, and binder ColoursFibre, tube, ribbon and binder colour codes and like-for-like splicing
7.7Splicing Loose Tube Fibres to Fibre RibbonsSplicing loose-tube fibres to ribbon fibres
7.8Spliceless Joints in High Capacity Fibre CablesSpliceless joints in HCFC — leaving a loop at installation
8.1PreparationHousing terminations in accommodation suited to the environment
8.2Optical fibre terminationTerminating fibres on factory pigtails
8.3Pigtail AttachmentHousing the pigtail splice in termination cassettes/ODFs
8.4Through-splicing at ODFsWhen fibres are through-spliced at an ODF instead of terminated
8.5DISAC and DISAF cablesManifolds for DISAC/DISAF cables so metallic parts cannot be touched
8.6Fibre Access Terminations (FATs)Fibre access terminations and NTPs for end users; points to 30179 and 31200
9.1GeneralSite acceptance tests — who does them and what they confirm
9.2Optical testingStandard OTDR testing at 1550 nm — what is produced
9.3Testing at 1310 nm and/or 1625 nm by ExceptionExtra testing at 1310/1625 nm when the design asks for it
9.4Optical fibre characterisation testingFibre characterisation for DWDM or dark-fibre customers
A.1Schedule of optical testsThe schedule of optical tests and how it relates to the design values in 30160
A.2Optical backscatter testing by OTDROTDR backscatter testing method
A.3Requirements for splice lossSplice loss targets
A.4Total Insertion Loss – connector to connectorTotal insertion loss connector-to-connector — the test method
A.5Permissible insertion lossHow permissible insertion loss is worked out and endorsed
A.6Polarisation mode dispersion and chromatic dispersionPMD and chromatic dispersion testing — when required

Standards this one points to