Clause map — what each clause deals with

1PurposeGuidance on installing telecoms cables and cable route
2ScopeWhat it covers and who it is for
3DefinitionsDefinitions and abbreviations
4Construction of New Cable RouteConstructing new cable route — the extent of the works
4.2GeneralGeneral rules for new route — position relative to the rail, access
4.2.1Limited SpaceReduced clearance from the running rail where space is limited — tunnels, bridges, structures
4.2.2Route between tracksRoute between tracks (ten-foot)
4.3.1Product OverviewDI-SAC product overview
4.3.2InstallationDI-SAC installation principles
4.3.3Securing DI-SAC with Ground AnchorsSecuring DI-SAC with ground anchors
4.3.4Interfacing with Cable RoutesDI-SAC entering existing cable route
4.3.5Interfacing with Bridges and ViaductsDI-SAC at bridges and viaducts
4.3.6Interfacing with UTX and URX ManholesDI-SAC through UTX/URX manholes
4.3.7Interfacing with Cable Joint BaysDI-SAC joint bays
4.3.8Sheath GapsDI-SAC sheath gaps before housings
4.3.9Foot Crossings and Farm CrossingsDI-SAC at foot and farm crossings
4.3.10Vehicular Access PointsDI-SAC at vehicular access points
4.3.11Hazards and ObstructionsDI-SAC hazards and obstructions to avoid
4.4.1GeneralConcrete troughing — general, points to 00013
4.4.2Troughing LidsLaying troughing lids — stagger
4.4.3Buried RoutesUsing buried routes
4.4.4VandalismSecuring troughing in vandalism areas
4.4.5Ballast ShoulderNot disturbing the ballast shoulder
4.4.6Crossing Traction Feeder CablesCrossing traction feeder cables with ramped support
4.4.7Joint BaysJoint bay construction
4.5Retaining Walls for Joint Bays & CabinetsRetaining walls and platforms for joint bays and cabinets
4.6.1GeneralWhen elevated route is used
4.6.2GRC and GRP Route ConstructionBuilding GRC/GRP elevated route
4.7.1GeneralConstructing new manholes
4.7.2Covers and FramesManhole covers and frames — classes
4.8Buried Duct RoutesBuried duct routes — searches first
4.8.1Requirements for all Duct Routes (Except DBS)Requirements for duct routes
4.8.2Routes Through Station PlatformsRoutes through station platforms
4.9Hard Surface Walkway Duct RoutesDucts in hard-surface walkways
4.10Public CrossingsPublic crossings
4.11Under Track CrossingsUnder track crossings — the civils standards that apply
4.12Installation of Distribution Cabinets and Pole-Mounted BoxesInstalling distribution cabinets and pole-mounted boxes
5Renovation of Existing Cable RoutesRenovating existing cable routes
6Cable SlackLeaving cable slack for future joints
7Work in Tunnels and Restricted AreasLaying and installing cable route and cables in tunnels, on bridges and viaducts — the civils rules that apply and who to involve
8TimberingTimbering excavations
9Anti-Corrosion Protection for Ferrous Metal WorkGalvanising ferrous metalwork
10Surplus and / or Scrap Material Recovery and DisposalSpoil and scrap disposal
10.2Waste WaterWaste water disposal
11AccessSite access rules
12Handling of Materials Containing AsbestosHandling asbestos
13Buried Services SearchesBuried services searches — the standard that applies
14As-Built RecordsKeeping as-built records during installation; points to 30142