Limits and Test Method of Induced Voltages on Telecommunications Cables due to Electrification Systems

Issue 2, 06 March 2010 · Copper design & immunisation

The induced-voltage limits (longitudinal VL and transverse VT) on copper telecoms cables in AC electrified areas, and the test process used to prove them before, during and after electrification changes

Clause map — what each clause deals with

1PurposeWhat the standard is for: defining test limits and methods for voltages induced on copper telecoms cables by AC electrification, in normal and credible failure modes, to protect staff, equipment and service quality
2ScopeApplies to lineside telecoms cables in AC electrified areas when electrification, traffic or the telecoms cables themselves change; sits under the GE/RT8016 interactions plan
3.1Designated Project Engineer (DPE)What the DPE does before a change: risk assessment to set the level of modelling, test plan, tests, reports and the commissioning certificate
4.1AbbreviationsAbbreviations used (BT, RC, OHLE, FTE, VL, VT and so on)
4.2DefinitionsDefinitions including accessible voltage, booster transformer, longitudinal and transverse voltage, hot wire working
5IntroductionHow AC traction induces a longitudinal voltage along lineside conductors and the risks that follow (shock, equipment damage, noise)
6.1ProcessThe overall compliance process (Figure 1): define route, model, test plan, pre-change tests, upgrade, commissioning tests, post-commissioning tests, report
6.2Definition of RouteDefining the telecoms cables on the route and the maximum circuit length of each section
6.3ModellingAssessing expected VL by modelling or calculation before the change, scaled to the risk
6.4Test Plan & Migration PlanWhat the test plan must contain — tests, locations, pairs used, electrification and traffic conditions
6.5VL and VT In-Traffic TestsPre-change in-traffic VL/VT tests, minimum 2 hours at peak traffic (longer for big changes)
6.6ReportResults go to the DPE; changes may start once acceptance criteria are met
6.8Commissioning TestsTests when commissioning AC electrification: load bank (only for new system types), short circuit at the worst-case location, degraded-condition tests not normally required
6.9Post-Commissioning TestsIn-traffic VL/VT tests after the change (2 hours minimum at peak); hot wire working if VL limits are not met
6.10Reports & CertificateThe DPE's modelling report, test report and the Telecommunications Commissioning Certificate (Appendix A)
7.1Normal ConditionsThe longitudinal voltage limit under normal conditions — Table 1, time-dependent: 60 V rms steady state (>300 s), 65 V up to 300 s, rising to 370 V for 20 ms events
7.2Degraded ConditionsHot wire working is invoked under degraded conditions (booster/autotransformer outage, missing screening conductor) unless the risk has been shown tolerable
7.3Fault ConditionsFault-condition VL limits (Table 2, time dependent) and the 645 V rms absolute maximum to protect lineside equipment
8Transverse Voltage LimitsTransverse (pair-to-pair differential) voltage: 1 mV rms psophometrically weighted under normal conditions, with permitted excursions
9.1Test ProcessThe step-by-step VL/VT set-up and test process (Table 3)
9.2Selecting Test PairsChoosing the cable and pairs that give the least protection (longest cable, worst screening)
9.3Tests Prior to Terminating CableInsulation resistance and conductor resistance/balance tests on the test pairs before termination, recorded on the Cable Test Sheet
10.1Terminating Test Pairs for Longitudinal VoltageHow the VL pair is earthed at the remote end (30 ohm or better earth, remote from the railway)
10.2Tests on Terminated Longitudinal Voltage PairsResistance to return rail (>1 ohm) and VL loop resistance checks
10.3Test Equipment Specification for Longitudinal Voltage - ContinuousMinimum spec for the recorder used for continuous VL measurement
10.4Test Equipment Specification for Longitudinal Voltage - Short CircuitMinimum spec for recording VL during short-circuit tests
11Transverse Voltage Test MethodWhy VT is measured (speech clarity, digital interference) and the 300–3000 Hz weighting
11.1Tests on terminated transverse voltage pairsResistance check on the 600 ohm terminated VT pair before measuring
11.2Psophometric transverse voltage measurementsITU-T O.41 psophometric weighting and how to apply it
11.3Unweighted transverse voltage measurementsWhen an unweighted VT measurement is needed (trackside system compatibility evidence)
11.4Test Equipment Specification for Transverse VoltageMinimum spec for VT measurement equipment
11.5Using Digital Post-ProcessingApplying the weighting filter by post-processing a digitised recording
Appendix ATelecommunications Commissioning CertificateThe certificate the DPE signs off after successful verification
Appendix BCable Test SheetThe spreadsheet used to record pair tests and calculate derived values

Standards this one points to