NR/L2/TEL/30400/002

GSM-R Availability Assessment for ETCS Traffic

Issue 1, 05 September 2026 · GSM-R & radio

How an ETCS project assesses whether the GSM-R and FTN infrastructure is available/reliable enough for ETCS — availability model, apportionment model against delay-minute targets, and the interfaces with DDaT, performance modellers, signalling and the Route

Clause map — what each clause deals with

1PurposeDesign-stage guidance for setting the telecoms availability requirements that ETCS needs
2ScopeMethodology and criteria for availability and apportionment of telecoms infrastructure along a line of route
3Roles and ResponsibilitiesRACI for the availability assessment — project, DDaT, performance modelling team, signalling, Route
4DefinitionsPoints to NR/L2/TEL/30400 for terms
5.1IntroductionChecking the infrastructure against the route's business performance targets
5.2Availability ModelQuantitative model (e.g. reliability block diagrams) of GSM-R and FTN resilience, with scenarios and configurations
5.3Apportionment ModelTranslating predicted failure rates into delay minutes where the route has a delay-minute target
6.1IntroductionAvailability is never assessed in isolation from the key interfaces below
6.2Digital Data and Technology Telecoms OperationsDDaT receives the availability requirements and proposes infrastructure options
6.3Performance Modelling TeamThe project appoints a qualified performance modelling team (e.g. Systems Engineering – Reliability)
6.4Signalling TeamSignalling design constraints fed to the project and DDaT
6.5The RouteThe Route is shown how availability affects delay minutes and the benefit of alternative architectures