NR/L2/TEL/30025

Standby Power Supply Requirements for Telecommunications Equipment

Issue 5, 02 December 2017 · Housings, earthing, power & masts

How long NR telecoms equipment must keep running when the mains fails, and how a designer decides the standby arrangement (tiers, batteries, UPS, generator)

Clause map — what each clause deals with

1PurposeWhat the standard is for: keeping NR-owned telecoms equipment running for a set period after the normal supply is lost, with a whole-life-cost view rather than 'biggest battery wins'
2ScopeApplies to design and installation of new and renewed standby power systems, to assessing existing ones, and to their maintenance
3DefinitionsTerms used: battery bank, battery string, monobloc, concurrently maintainable, AIP, DNO and so on
4BackgroundWhy NR is moving away from long battery autonomies as the default — cost, manual handling and the availability of alternatives
5.1Initial assessmentOptions the designer has to show they considered before sizing batteries: improving the incoming power infrastructure, generators, alternative supplies
5.2ProcessThe three-stage assessment — criticality of the telecoms system (Stage 1, with NR/L1/TEL/30102 as a guide), availability of the proposed power infrastructure (Stage 2, Tier 1–4 table), then whether a UPS is needed (Stage 3)
6ApprovalStandby arrangements are approved by the National Telecoms Asset & Performance Manager through the Approval in Principle (AIP)
7Rectifier/Charger requirementsWhat the rectifier/charger must do: display load current, voltage and temperature, be isolatable and labelled, support the battery correctly
8Battery Bank requirementsDesigning the battery bank — smaller, lighter monoblocs to cut manual-handling risk, siting away from the equipment where possible, manufacturer's installation instructions
9RecordsDesigned standby times are recorded in Ellipse by the Project Engineer once commissioned
10Maintenance of Standby Power SuppliesMaintenance is to NR/L3/TEL/30081
Appendix ACriticality RequirementsThe Tier 1–4 criticality table and flow chart — how many mains sources, redundancy and generator provision each tier implies
Appendix BSuggested Tier levels and standby times for Telecoms SystemsThe look-up table of minimum and typical standby durations by asset type — e.g. FTN core/access/FTNx node 4 h minimum (12 h typical), transmission/IP with generator 30 min, PETS and tunnel emergency comms 4 h, voice recorders 4 h

Standards this one points to