Clause map — what each clause deals with

1PurposeGuidance for surveying and designing telecoms cables and cable routes
2ScopeWhat the guidance covers and who it is aimed at (principal contractor / project)
3DefinitionsDefinitions and abbreviations (ATEH, BOP, GRC/GRP, SCT, UTX and so on)
4Tools for Cable Route SurveyThe kit a cable route surveyor should carry — measuring wheel, mandrel, gas detector, CAT scanner and so on
5.1SurveyWhat the surveyor is expected to know and capture
5.2Use of Survey PackagesUsing approved video/track-survey packages instead of walking everything
6Key Cable and Route Survey AspectsThe checklist of things to look at on a cable route survey — the section juniors should read first
6.1AC AreaSurveying in AC areas — screening conductor and earth farms
6.2Asbestos Cable RouteAsbestos cable route — what to do
6.3Assessment of Concrete Troughing DamageAssessing damaged concrete troughing and when it is replaced
6.4Ballast BoardsBallast boards — where to record them
6.5Buried Troughing RouteBuried troughing route — why it is not reused and what to record
6.6.1Light Coverage of Ballast or VegetationLight ballast/vegetation cover — lid tilting
6.6.2Ballast ClearanceClassifying ballast clearance per metre
6.6.3Vegetation ClearanceClassifying vegetation clearance per metre
6.8Concrete BasesConcrete bases for distribution cabinets and BOPs
6.9Copper CablesWhat to record when surveying copper cables, including length allowances
6.10.1Under Road Crossings / Level CrossingsUnder-road and level crossing ducts — assessing and renewing
6.10.2Farm CrossingsFarm crossings
6.10.3Under Track CrossingUnder-track crossings — checking existing UTX capacity, S-type UTXs, boring new ones
6.10.4Foot Crossing Routes Including Hard Surfaced and Through YardFoot crossings, hard-surface and yard walkway routes
6.11Deployment of DBSDBS (direct buried) — withdrawn and not to be used
6.12Deployment of DI-SACDI-SAC treated as a form of cable route — survey implications
6.13Earthing for Lineside CabinetsEarthing for lineside cabinets with active equipment
6.14Earth SystemsRecording existing and proposed earth farms
6.15ElectrificationRecording the electrification type across the site
6.16Equipment Rooms and BuildingsSurveying equipment rooms and buildings — manholes and duct capacity
6.17Building Entry Point and Duct SealsBuilding entry points and duct seals
6.18Elevated Cable RouteElevated cable route on walls and parapets
6.19Fragile CablesKnown fragile cables — care when lifting lids
6.21Joint BaysJoint bays — siting outside the main route, closures
6.22Lift and Re-lay or Re-alignment of RouteWhen a route is lifted and re-laid
6.23Re-alignment of RouteRe-alignment without lifting
6.24.1Surveying and CheckingSurveying manholes safely and what to check
6.25New Cable RoutesWhen a new parallel route beats renovating the old one
6.26Obsolete Cable RoutesRoute types classed as obsolete
6.27Optical FibreWhat to record when surveying optical fibre cables
6.28ParallelismParallelism with feeders and grid lines — extra screening
6.29Red / Green Zone WorkingRed/green zone working and possession needs
6.30Restricted WorkingSurveying restricted areas — tunnels and cuttings — and recording the work needed inside them
6.31Retaining WallsWhen a retaining wall is needed for a manhole
6.32Roads and Street Work ActStreet works and the NRSWA implications
6.33Rodding Duct RoutesRodding and proving duct routes
6.34Route ObstructionsRecording route obstructions
6.35Route TransitionsRoute transitions between route types
6.36Route Through Stations (Ducts)Routes through station platforms — duct occupancy
6.37Surplus, Scrap Material, Recovery and DisposalScrap and surplus — measuring and recording
6.38T-PiecesWhere T-pieces are needed
6.39Troughing LidsTroughing lids — what defects to record
6.40Troughing Route SupportRoute support on slopes
7.1GeneralWhat a design submission must be — the general rules
7.2ContentThe minimum contents list of a cable/route design submission
7.3Title PageTitle page contents
7.4Contents PageContents page
7.6Design AssumptionsDesign assumptions section
7.7Location Maps and GPS CoordinatesLocation maps and GPS coordinates
7.8.2Signalling InfrastructureSignalling infrastructure to show
7.8.3Electrification InfrastructureElectrification infrastructure to show
7.8.4Existing Telecoms InfrastructureExisting telecoms infrastructure to show
7.8.5Existing or Proposed FTN & GSM-R Infrastructure (where applicable)FTN and GSM-R infrastructure to show — nodes, BTS, joints, sheath gaps, UTXs
7.8.6MiscellaneousMiscellaneous items — grid lines, roads, chainage
7.9Transmission Design Information (where applicable)Transmission design information
7.10PDR and Engineering Clearance (where applicable)PDR and engineering clearance
7.11Design Concessions (Non-compliancy and Derogation)Design concessions — non-compliance and derogation
7.12Survey NotesSurvey notes section
7.13PhotographsPhotographs section
7.14Bill of QuantitiesBill of quantities — free issue vs contractor supply
7.15Copper DetailsCopper details — the schedules required
7.15.1Copper Cable Schedule that identifies for each length of copperCopper cable schedule — what each length must show
7.16Fibre Cable DetailsFibre cable details — the main cable schedule
7.17Fibre Splice DiagramFibre splice diagram — what it must show
7.18Screening Conductor DetailsScreening conductor schedule
7.19Physical Diversity RequirementsPhysical diversity diagrams per node
7.20Structural ScheduleStructural schedule — walls, platforms
7.22Designer's Risk AssessmentsDesigner's risk assessments
7.23Tunnel Information (Cable Provision)Tunnel information proforma — what the design submission must record for each tunnel (length, bores, existing route, cable provision)
Appendix AJoint Bay ArrangementsJoint bay arrangement drawings
Appendix BExample of Route Support (PreviouslyExample route support (ex DR/FTN(D&D)/052)
Appendix DTunnel InformationTunnel information proforma

Standards this one points to