Clause map — what each clause deals with

1PurposePerformance specification for cable troughing products
2ScopeApplies to all products that protect and contain cables on NR infrastructure
3DefinitionsDefinitions — trough, lid, elevated route and so on
4IntroductionBackground — the scale and types of NR troughed routes
5Material make up and cable trough dimensionsMaterial families and standard trough dimensions (C/1/x sizes)
6Material quality controlManufacturer quality control
7Product acceptanceProduct acceptance route
8.1GeneralGeneral robustness for manual or mechanical installation
8.2Traditional concrete troughingTraditional concrete troughing
8.3Cement based troughingCement-based (GRC) troughing
8.4Reduced weight traditional concrete troughingReduced-weight concrete troughing preferred
8.5Non-cementitious troughingNon-cementitious (polymer/GRP) troughing and banned materials
8.6Product service lifeService life
8.7Immersion in waterWater immersion
8.8ToxicityToxicity
8.9Material fire performanceFire performance of materials
8.10Resistance to corrosionCorrosion resistance of fittings
8.11Traditional concrete troughing and cement based productsSulphate-resisting cement requirements
8.12ColourColour
8.13Tolerance to climatic conditionsTemperature tolerance
8.14.1For ground level cable troughLids for ground-level troughing — securing and fit
8.14.2For elevated routesLids for elevated routes
8.15Trough lid security for high vandal risk areasLockable lids for high-vandal areas
8.16Trough alignmentTrough alignment inserts
8.17Cable exitCable exits — knock-outs
8.18Reinforcement for traditional concrete and cement based troughingsReinforcement — steel mesh and non-cementitious
8.19Surface finishSurface finish — smooth internals
8.20.1Troughing for ground level routesWeight limits for ground-level troughing
8.20.2Troughing for elevated routesWeight limits for elevated troughing
8.21.1Cable troughing for ground level routesDimensions and tolerances for ground-level troughing — the drawings
8.21.2Cable troughing for elevated routesDimensions for elevated troughing
8.22Installation instructions and guidanceInstallation instructions supplied with deliveries
9.1GeneralQualitative acceptance tests — overview
9.2Type testingType tests — deflection, compression, impact, temperature cycling, drop, cover, cable exit, vehicle
9.3Type testing – additional for non-cementitious troughingExtra type tests for polymer troughing — weathering, ESD, thermal movement
9.4Production testsProduction tests — cubes, finish, flatness, slump, gauging
10Sample testsSample tests on delivery
11DeliveryDelivery and palletising
12DocumentationDocumentation for product acceptance
13Accessories (including T-pieces, transition unit and curve troughing)Accessories — T-pieces, transition units, curves
Appendix ASurface finishAcceptable surface finish photos