FTN design & development specification (D&D)
SP FTN (D&D) 015
Environmental Testing of Copper Cable Termination Practices
Issue 1, Apr 2002 · FTN D&D specs & typical drawings
Test specification used to compare candidate copper termination blocks (Mondragon VX, Telsplice, Entrelec, 2BA link, Weidmuller, Porta Systems) under damp-heat cycling in an unconditioned cabinet. Background to why the FTN chose the VX module for lineside cabinets.
Clause map — what each clause deals with
| 1 | Introduction | Why termination practices were environmentally tested before FTN deployment. |
| 2 | Abbreviations | Acronyms (ETSI, FTN, IDC, NAMAS). |
| 3 | Glossary | Definitions of moisture barrier, Employer and Supplier. |
| 4 | Scope | Tests replicate worst-case temperature and humidity a termination sees on the lineside. |
| 5 | Deliverables | What the test coordinator must provide: venue, plan, method statement, tests, results, report, witnessing. |
| 6 | The Test Venue | Preference for an accredited independent test house and what it must offer. |
| 7 | The Samples | The six termination products under test. |
| 8 | The Tests | Damp-heat cyclic test regime in an IP65 cabinet: three cycles with desiccant, without, and doors open; test cable provided. |
| 8.1 | Testing Configurations | Moisture barrier used as a virtual earth; per-sample wiring arrangements with diagrams. |
| 8.1.1 | Sample 1: Mondragon VX Module | Three VX modules on DIN rail, outer ones to the barrier, pair 1 on the middle. |
| 8.1.2 | Sample 2: Telsplice Connector | Telsplice crimp on pair 2. |
| 8.1.3 | Sample 3: Entrelec Block | Four Entrelec blocks, outer ones to barrier, pair 3 on the middle two. |
| 8.1.4 | Sample 4: Weidmuller Block | Four Klippon blocks arranged as for Entrelec, pair 4. |
| 8.1.5 | Sample 5: 2BA Sliding Link Block | 2BA block mounting, link and barrier connections, pair 5 on crimped terminals. |
| 8.1.6 | Sample 6: Porta Systems 10 Pair Module | IDC module with all other pairs strapped to the barrier, pair 6 on module pair 5. |
| 8.2 | Measurements | Insulation resistance test voltage and the two readings per sample (A-B, A-barrier). |
| 8.3 | Frequency of Measurements | Logging intervals around the temperature fall and through each cycle. |
| 9 | Calibration of Test and Measurement Equipment | Calibration standard and traceability of test gear. |
| 10 | Results | Resolution of recorded readings and which two IR values to log per sample. |
| 11 | Documentation | Result sets, equipment details and real-time plots of chamber and cabinet temperature and humidity. |
| 12 | Management Requirements | Contents of the test plan (venue, dates, cycle times, equipment, report date). |
| 13 | References | Referenced standards. |