NR/L3/TEL/00061

Procedure for works impacting GSM-R

Issue 1, 01 March 2025 · GSM-R & radio

Clause map — what each clause deals with

1PurposeThe process for planning works near or affecting GSM-R masts and coverage — what a project must do
2ScopeWhat kinds of works and lineside activities can impact GSM-R
3Terms and DefinitionsTerms and definitions (APIS, DDaT, F061)
4Roles and responsibilitiesProject duty to notify DDaT using form F061
5Introduction to GSM-RIntroduction to GSM-R for non-specialists
6Impact of Project to GSM-R/Change CriteriaChange criteria — when a project must raise the form
7.1Common Safety Method – Risk Evaluation and AssessmentCSM-RA applies to GSM-R changes
7.2InteroperabilityInteroperability (CCS NTSN) compliance
8Form Completion InformationHow to complete F061
9DDaT ResponseWhat DDaT sends back
10Collaboration throughout projectKeeping DDaT in the loop through the project
11TimescalesWhen F061 is due (end of ES3)
12Close OutClose-out at project completion