Level 2 specification
NR/L2/TEL/30022
Engineering Assurance Arrangements for Communications Engineering Schemes and Services (formerly RT/E/P/30022)
Issue 8, 05 March 2022 · Design process, assurance & records
Clause map — what each clause deals with
| 1 | Purpose | What the spec is for: controlling the risk from changes to telecoms assets through engineering assurance |
| 2 | Scope | Applies to all design work for renewal, enhancement, extension and temporary works |
| 3 | Definitions | Definitions — AiP, AiO, DPE, CRE, acceptance and so on |
| 4 | Sponsors Instruction | The sponsor's instruction and what it should contain |
| 5 | Approval Strategy | The approval strategy — the schedule of deliverables the CRE submits |
| 6 | Approval in Outline (AiO) of Single Option Selection | Approval in Outline of the single option |
| 7 | Approval in Principle of Single Option Reference System Design | Approval in Principle of the reference system design |
| 8 | Contract Requirements – Technical for implementation | Contract Requirements – Technical for implementation |
| 9 | Acceptance of detailed design | Acceptance of the detailed design by the CRE |
| 10 | Entry into Service | Entry into service — which standards cover it |
| 11 | Engineering Completion | Engineering completion — which standard covers it, deviations |
| Appendix B | Recommended Information required for Approval in Principle | Recommended information for AiP of the reference system design |