onestop

FTN & GSM-R programme document

FTN&GSM-R QM WI 046

Detailed Site Survey Guidelines

Issue 01, Sep 2005 · FTN D&D specs & typical drawings

Work instruction for surveying and choosing GSM-R base station and FTN node sites: mandatory distance and siting criteria, desirable criteria, and the Excel site survey questionnaire with its panoramic photo requirements. Used by site surveyors and cell planners.

Clause map — what each clause deals with

1PurposeWhat the work instruction covers: siting criteria for NTPO infrastructure and the survey information to submit.
2ScopeApplies to locating GSM-R and FTN sites for safety, neighbours, property clearance and PDR.
3Reference DocumentationPoints to GT/TDINT100 distance criteria.
4DefinitionsNTPO, FTN, GSM-R, PDR, OHLE.
5ResponsibilitiesSurveyors and cell planners responsible for siting within all criteria.
6Site Survey Guidelines & CriteriaParent clause for mandatory and general siting criteria.
6.1Mandatory RequirementsMust-meet siting rules: NR land, separation from electrical plant, antennas, OHLE, rails, bonds, pylons, schools; signal sighting, tower height, coverage, site dimensions, node spacing, access.
6.2General Requirements - Site SurveyDesirable criteria: not between tracks, away from listed buildings and housing, walking distances, near existing masts and power, conservation areas, SSSI, adjacent to existing troughing.
7Site Survey QuestionnaireThe questionnaire is an Excel worksheet completed electronically for upload to the central GSM-R and FTN database to drive clearance, PDR, access, possessions and power.
8AppendicesFull questionnaire field list: site ID, location, mast type, adjoining land, topography, compound size, access, parking, electrical proximity, environment, power, photos, line IDs, ELR.